Nature of case:It was inconsistent with the policy of the adjudication scheme to allow an adjudicator’s award to be effectively rendered nugatory by raising a cross-claim that might or might not succeed.  The arbitrator had had jurisdication to make the award and the claimant was thereofore entitled to summary judgment for the sum awarded.