Citation: EWHC 727 (TCC)
Nature of case: It was held that the "main contract works" had been "certified substantially or practically complete" for the purposes of an adjudication clause in a sub-contract under a term contract and accordingly, the court had jurisdiction to entertain a claim by the main contractor.