Citation: 96 Con LR 69 TCC
Nature of case: This case concerns the scope of an adjudicator’s power to control the procedure of the adjudication. Specifically, it concerns an adjudicator’s excess of jurisdiction in failing to deal with a defendant’s objection to new issues being raised by claimant and adjudicator. This affected the fairness of the adjudication procedure. The case concerned entitlement to interest under an NEC contract associated with laying a gas pipeline.
See further information: [2004] BLR 352 TCC