0

Download your shortlist

Download All

Resources

Keating Chambers is committed to providing training and development to current and prospective clients. Our resources pages include:
Resource Icon 1

A catalogue of cases in which members have been involved;

Resource Icon 2

Issues of KC Legal Update, a quarterly publication comprising articles and interviews spanning a broad range of practice areas;

Resource Icon 3

Links to leading publications authored by our members; and

Resource Icon 4

Links to recent blogs, webinars and podcasts contributed by our members.

In addition to the regular open events, our barristers also offer in-house training seminars covering a broad range of relevant and topical developments in law. Please contact marketing@keatingchambers.com if you would like to find out more information.

Buckinghamshire Council v FCC Buckinghamshire Limited

13 December 2024

Citation: [2024] EWHC 3215 (TCC)

Facts The claimant and defendant had previously been parties to a waste management contract. Following a dispute, the claimant had been awarded a principal sum of approximately £9 million, which was subsequently paid by the defendant. An additional sum of approximately £90,000 was also identified and paid by the defendant at a later date. The present judgment concerned whether interest should be calculated from the date of judgment, or an earlier date specified by the claimant, and also whether the interest should be compound. The claimant argued for interest from the end of each contract year, compounded at 2% above the Bank of England base rate, as per the agreement. The defendant accepted the prescribed rate but disputed the start date and the compounding of interest.DecisionThe Judge decided that the claimant was entitled to simple interest at the prescribed rate from the due date. The agreement did not provide for compound interest and the claimant was therefore not entitled to claim it. The court rejected the defendant’s argument that interest should only accrue from the date of judgment because there was no contractual obligation before this point. The Judge found this…

Counsel

Justin Mort KC

BNP Paribas Depository Services Ltd & Anor v Briggs & Forrester Engineering Services Ltd

18 November 2024

Citation: [2024] EWHC 2903 (TCC)

The Court interpreted the provisions of an amended JCT Design and Build Contract 2016 with particular focus on the scope of a contractor's responsibility for additional and unforeseen works on site, and the legitimacy of suspension and termination notices.Facts The claimant (BNP) engaged the defendant (B&F) to design and construct stair pressurisation works in a 30-storey office tower. These works would include removing the existing system and installing an improved system. The contract was an amended 2016 JCT Design and Build contract. Works were complicated due to the presence of asbestos in the building. An issue arose between the parties as to the extent of the asbestos removal works, and whether B&F was obligation to carry out additional  surveys and the asbestos removal works  that were subsequently required, as well as additional structural works that had not initially been foreseen as part of its original scope of work.When further asbestos was discovered, the works were halted, and B&F issued a suspension and then termination notice. BNP treated this as repudiatory breach and sought declarations that B&F was not entitled to serve either the suspension or…

Counsel

James Frampton

Estate Management v Junior Sammy

29 October 2024

Citation: [2024] UKPC 33

David Thomas KC has successfully argued before the Privy Council that the decision of the Court of Appeal of Trinidad and Tobago in EMBD v Junior Sammy Contractors should be upheld.  

Counsel

David Thomas KC