Citation: [2024] EWHC 2903 (TCC)
The Court interpreted the provisions of an amended JCT Design and Build Contract 2016 with particular focus on the scope of a contractor's responsibility for additional and unforeseen works on site, and the legitimacy of suspension and termination notices.Facts The claimant (BNP) engaged the defendant (B&F) to design and construct stair pressurisation works in a 30-storey office tower. These works would include removing the existing system and installing an improved system. The contract was an amended 2016 JCT Design and Build contract. Works were complicated due to the presence of asbestos in the building. An issue arose between the parties as to the extent of the asbestos removal works, and whether B&F was obligation to carry out additional surveys and the asbestos removal works that were subsequently required, as well as additional structural works that had not initially been foreseen as part of its original scope of work.When further asbestos was discovered, the works were halted, and B&F issued a suspension and then termination notice. BNP treated this as repudiatory breach and sought declarations that B&F was not entitled to serve either the suspension or…
Counsel