Stellite Construction Ltd v Vascroft Contractors Ltd

Citation: 165 ConLR 108

An adjudicator had not breached the rules of natural justice in deciding that time for completion of a construction project was at large. However, he had exceeded his jurisdiction in going on to determine a reasonable date for completion, and that part of his decision could be severed.