Citation: BLR 357 (TCC), [2009] EWHC 560 (TCC), 124 Con LR 102
Nature of case: An engineering company was granted an interim injunction requiring another company to deliver to it certain quality assurance documentation, as there was a serious issue to be tried as to whether there was a binding agreement between the parties with regard to conditions to be fulfilled before the documents were released.