Citation: Con LR 119; CILL 1583 & LTL 2/11/99
Nature of case: Claims and counterclaims for damages for delay in completion of sub-contract work allowed in part. Delay was held to be causative in part only of the delay in completion of main coontract. Claim for contribution by sub-contractor to damages paid by main contractor disallowed.