Citation: 122 Con. L.R. 66, BLM Vol. 26 No. 4 TCC, [2009] EWHC 73 TCC
Nature of case: This case related to the scope of the court’s jurisdiction to review adjudication decisions in Part 8 proceedings. The main issue was the circumstances in which a court could review an adjudicator’s decision as to whether the defendant sub-contractor’s standard terms and conditions had been incorporated into the contract between the parties.