Citation: BLR 437 CA
Nature of case: This concerns the point at which the contractor’s right to payment arises and whether (in an ICE 6th contract) the issue of a certificate is a condition precedent to payment. The right to claim interest on a sum which should have been certified becomes statute-barred six years after the accrual of the right.
See other reports: [2005] 101 Con LR 52 CA [2005] EWCA Civ. 814 LAWTEL CA [2005] CILL 2276 and BLM Vol 22 No 9 p.1 CA