Henry Boot Construction Ltd v Alstom Combined Cycles Ltd (No. 2)

2005

Citation: 101 Con LR 52 CA

Nature of case: This is a case considering the time at which the civil engineering main contractor’s right to payment arose in a power station project in North Wales and whether (under ICE 6th) the issue of a certificate is a condition precedent to payment. The right to claim interest on a sum which should have been certified becomes statute-barred six years after accrual of the right. 

See other reports: [2005] BLR 437 CA [2005] EWCA Civ. 814 LAWTEL CA [2005] CILL 2276 and BLM Vol 22 No 9 p.1 CA