Citation: Con LJ Vol. 21 No. 4 321
Nature of case: In an arbitration award from Hong Kong, published with the consent of arbitrator and parties, it was held that under clause 23 of the Hong Kong RICS Contract an architect could grant an extension of time for instructions or variations only causing delay when the date for completion was past.