Citation: 102 Con LR 102 TCC
Nature of case: Already reported BLR. This is a belated Con LR report of the TCC’s consideration of the proper procedure for appointment of an adjudicator under the Scheme for Construction Contracts where a nominated person was unable or unwilling to act as adjudicator.
See other reports: [2004] BLR 172 TCC