0

Download your shortlist

Download All

Jerram Falkus Construction Limited v Fenice Investments Inc (No. 3)

21 July 2011

Citation: EWHC 1935 (TCC)

Nature of case: The parties entered into a JCT Design & Build Form 2005 with amendments.Feniselevied liquidated damages for works delayed and Jerram counter claimed for loss and expenses, further contending Finesse’s own conduct as responsible for preventing completion of works. In the thirdadjudication between the parties Jerramwas found responsible for the delayswithno act of prevention by Fenisewhich rendered time at large. The court agreed with the decision of the third adjudicator. 

Link to Judgment 

Counsel

William Webb KC
William Webb KC