Citation: Con LJ 299
Nature of case: Following the trial of the first ten preliminary issues, the court had held in June 2006 that Cleveland Bridge had repudiated the steel sub-contract at Wembley Stadium. This judgment decided that temporary roof works designed to support the roof during construction did not form part of the works covered by the fixed lump sum agreed.