Citation: CILL 2688 TCC
Nature of case: In proceedings by sub-contractor OSC to enforce an adjudication decision against main contractor IDC, IDC argued that the dispute related to the final account rather than an interim payment and that the referral expanded the dispute beyond that set out in the notice of adjudication. The court rejected these arguments and held that to raise jurisdictional arguments there must have been at least a protest in the adjudication.