Citation: CILL 2012 TCC and [2003] EWHC 1390 (TCC)
Nature of case: On breach of the rules of natural justice by an adjudicator in basing his decision upon the final report of an appointed planning expert without giving the parties the opportunity to review it.
This was so even though the adjudicator had not wrongfully delegated the making of the decision to the expert.