Shawton Engineering Ltd v DGP International

27 November 2015

Citation: CILL 2306 CA

Nature of case: This case arose from a design sub-sub-contract relating to a process plant in Sellafield for handling nuclear waste. The issue arose as to the circumstances in which a contracting party could lawfully terminate a contract for delay in performance where the obligation was to complete within a reasonable time. 

Link to Judgment 

See other reports: [2006] Con LJ Vol. 22 No. 2 p. 129 CA [2006] BLR 1 CA [2005] All ER(D) 241 CA