Citation: 90 Con LR 86 TCC
Nature of case: Concerns an application by Part 20 CPR defendants for an order under Part II CPR that a Court had no jurisdiction to hear a dispute between sub-contractors and sub-sub-contractors. They argued that there could be no claim for indemnity until the main contract liability was ascertained and that the main contract dispute resolution provisions governed sub-sub-contract disputes.
See other reports: [2005] BLR 395 CA [2005] EWCA Civ. 894 LAWTEL CA [2004] BLR 409 TCC [2003] 90 Con LR 115 TCC